1. Ensure selected installation site satisfy all requirements of local quality control dept, and obtain permission of them before installation of Construction Hoist.
2. Ensure the selected installation site has road and yard to transport and stack the hoist and its parts.
3. To protect stabilization of the hoist you should make the machine near the building, but the distance between moving parts of hoist and fixed constructing equipment should be not less than 250mm.
4. Make sure that there is power supply on the erection site. Provide a power box specialized for the hoist and a switch for each cage.
5. The main power of site should connect with transformer substation by 3×25+2×10mm2 cable. Each cage has one cable. Increase section of cable with the distance increased.
6. Make sure that there is lifting equipment and tools at the erection site.
7. Cast a foundation according to manufacture's needs.
8. Prepare pre-embedded parts and fixed parts of tie-in.
9. Check parts according to packing list during transporting and storage. If missing or damage, should repair or replace in time.
10. According to equivalent ordinance and requirement to set up grounding protection device, its grounding resistor is less than 4Ω.
CONTACT US for all kinds of construction hoist and other construction machines such as Tower Crane, Derrick Crane, Suspended Platform, etc.
Tel: 0086 024 26210512
Email: bq@bq-sy.com
Web: www.bq-sy.com
Subscribe To Our Newsletter:
Get Updates, Discounts, Special
Offers and Big Prizes!